Project: Regala Gymnasium
Owner: St. John the Baptist Parish
Architect: Meyer Engineers, LTD.
Description: This is the new construction of a 18,000 SF gymnasium in Reserve, La. The project consists of a pre-engineered metal building with a new concrete slab on driven timber piles. The building will have CMU to 12’ with metal panels above, a full-court basketball court with volleyball equipment, telescopic gym seating, concessions, and a mezzanine level with offices. The site will also have 40,000 SF of asphalt paving.
Start Date: June 2010
Completed Date: December 2011
Amount: $2,285,300
Project: New Orleans City Park Popp’s Fountain Pavilion
Owner: City of New Orleans
Architect: Waggonner & Ball Architects
Description: This project is the new construction of a 5,500 SF clear span tent structure on a 15,000 SF patio, to replace one that was destroyed during Hurricane Katrina. The tent will have permanent structures attached consisting of a service pavilion, bride’s room, and open pavilion. The patio is accented with an overhead aluminum trellis, vertical aluminum screens and a stainless steel cable trellis. Start Date: September 2010
Start Date: September 2010
Completion Date: October 2011
Amount: $2,586,800