Project:
 Sharp Station-New Classroom Space & restroom Renovations
Owner: East Baton Rouge Parish School Board
Architect: Fusion Architecture
Description:  The project consist of 3 new 800 square feet classrooms
retrofit with VCT and rubber base, marker/tack boards, projection screens, ceiling mounted projectors, storefront glass and solid core wood doors. The classrooms will also have security cameras installed in each.  There are two existing bathrooms that will be completely renovated and we will be adding a third bathroom.  This will consist of all new plumbing fixtures, toilet partitions, accessories, and a new epoxy flooring system.
Start Date: October  2007
Completion Date: December 2007
Amount:  $204,688







Project:
 Nicholson Apartments 
Owner: LSU 
Architect: LSU 
Description: The project consists of cleaning, repairing and re-painting all doors, side panels and pressure washing all 31 married student housing buildings on campus. 
Start Date: November 2006 
Completion Date: March 2007 
Amount: $81,150 















Project:  LSU EBL Cattle Shade Structures

Owner: Louisiana State University AG Center

Architect \ Engineer: Roger Husser, P.E. LSU

Description:   The project consists of four pre-engineered metal buildings with drilled shaft foundations.

Start Date: December 2006

Contract time: February 2007

Amount: $79,000




















Project:
 Developmental Storage Facility 
Owner: Louisianan State University AG Center 
Architect \ Engineer: Roger Husser, P.E. LSU 
Description: The project consists of a new ground up Departmental Storage Facility. Sitework, Concrete, Reinforcement Steel, Miscellaneous Steel, Painting, Fire Extinguishers, Metal Building, Doors, and Electrical. 
Start Date: July 2006 
Completion Date: January 2007 
Amount: $124,500